Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,547 questions

4,800 answers

791 comments

Register its Free

Download here

NEC ECC: Contractor claiming time for reviewing subcontractor award documentation?

0 votes
90 views
Under Option C, the contractor included in his quotation time for a QS to procure the services of a subcontractor and a Design Manager to give technical guidance during the procurement phase. The services to be provided by the subcontractor is an agreed compensation event. My understanding is, a) if this is extra to the working hours of the QS and Design Manager and impact on defined cost, or
b) additional resource is brought in to carry out the subcontractor review,

then it is a valid assessment. Otherwise I'm inclined to reject their point.
asked Dec 6, 2017 in NEC3 Compensation Events by Seetan1976 (150 points)  

1 Answer

0 votes
 
Best answer
Main Options C and D often lead to disputes regarding the inclusion of staff costs in CE quotations.  The basic principle is; the total Defined Cost with the CE less the total Defined Cost without the CE.  Although these resources (QS and Design Manager) may be allocated full time, the issue of preliminaries thickening often arises.  This is where the effect of numerous CE's, due to additional scope and disruption, requires supplementary resources to be brought in.  On it's own this is not a CE, although as Jon Broome has previously suggested, the PM may instruct this as a change to the Works Information, where acting sensibly.

Consider a 'project wide' view of such matters rather than a CE by CE basis and agree a sensible way forward.  Many projects now tender a percentage in the contract data to price for this very issue, especially as the nature of Main Option C anticipates change throughout the project life.
answered Dec 6, 2017 by Andrew WI (9,470 points)