NEC ECC: Archaeological Watching Brief

+1 vote
210 views
Bit of a broad question but can anyone advise on how to include for an archaeological watching brief when preparing Work Info pack for earthworks project?

Thanks
asked Nov 26, 2017 in NEC3 General by Greg (210 points)  

1 Answer

+1 vote
 
Best answer
You need to clearly define in the Works Information what your expectations are for a "watching brief". If there is a significant risk of archeology then a survey should be carried out and the results included in the Site Information. Also you may want to consider using the Supervisor to closely monitor the earthworks in addition to placing an obligation on the Contractor in the Works Information. Do some research with the relevant bodies to find out what good practice is for a "watching brief". For example here's a link to a CIRIA guide that seems relevant:

https://www.ciria.org/ItemDetail?iProductCode=C672&Category=BOOK&WebsiteKey=3f18c87a-d62b-4eca-8ef4-9b09309c1c91

You're Works Information would then need to place an obligation on the Contractor to follow good industry practice in relation to working in the vicinity of known or potential archeological sites. If there is a significant risk then you may want an archeologist on-site to monitor in which case you will need another obligation in the Works Information for the Contractor to co-operate with the archeologist in respect of the programming of the works (see ECC clause 25.1).
answered Nov 27, 2017 by Neil Earnshaw (15,490 points)