NEC ECC: Direct fee and subcontract fee on NEC3 ECC option E contract

+1 vote
472 views
If the direct fee and subcontract fee are applicable on the defined cost. What is the equipment over head, design overhead and people overhead used for - would this not fall part of the direct fee?
asked Nov 24, 2017 in NEC3 Contract Data by anonymous (1,580 points)  

1 Answer

+1 vote
 
Best answer
No, these three make up Defined Cost and are intended to avoid the need for the calculation of minutae when compensation events occur, so

- the percentage adjustment for listed Equipment is normally a negative percentage adjustment from a standard list, thus avoiding the need to justify (argue over) the costs of Contractor owned Equipment as well as produce an invoice for hired in  Equipment;

- the percentage for People overheads is to avoid the need for calculating the on-Site minutae of the costs listed in People 41 of the Shorter Schedule of Cost Components;

- the percentages for  design overheads is to avoid the hassle / complexity of calculating design office overheads on top of what is paid for an individual designer working outside the Working Areas.
answered Nov 24, 2017 by Jon Broome (46,270 points)