The Project Manager has given an instruction to change the Works Information. Is this a compensation event?

+1 vote
375 views

 The Project Manager has given an instruction to change the Works Information. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager giving an instruction to change the Works Information is a compensation event except:

  • If a change is made in order to accept a Defect or
  • If a change to the Works Information provided by the Contractor for his design is made at the Contractor’s request or
  • If a change to the Works Information provided by the Contractor for his design is made to comply with other Works Information provided by the Employer (see Clause 60.1(1)).
answered Oct 10, 2012 by BuiltIntelligence (870 points)