Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,308 questions

4,509 answers

591 comments

34,759 users

Register its Free

Download here

NEC TSC: How does Contractor go about changing a main subcontractor in TSC?

0 votes
47 views
If the contractor wants to change the subcontractor for no other reason than 'national procurement strategy' can the contractor do so? For example changing the subcontractor that maintains the chillers/ac
asked Nov 15 in NEC3 General by anonymous   1 4
   

1 Answer

+1 vote
You can do this, but it would be by either :
- when the Subcontractor's subcontract term finishes i.e. the the end of the 'service period'; or
- via the termination procedures of the contract : this would be expensive as it would be for a reason other than those listed and consequently, the termination payment would include amount A4 which is for "The direct fee percentage applied to ... any excess of the total of the Prices at the Contract Date over the Price for Services Provided to Date"
answered Nov 16 by Jon Broome (25,100 points)