Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,671 questions

4,954 answers

861 comments

Register its Free

Download here

JCT - Is the contractor liable to carryout and complete the design in D&B contract?

0 votes
118 views
If the Contractor is taken the responsibility of carrying out and complete the design in  D&B Jct contract is it okay? and what are the consequences of taking this responsibility?
asked Nov 7, 2017 in JCT Contracts by Andrea   1

1 Answer

0 votes
 
Best answer
The design responsibility in this scenario is exactly the same as any other obligation to carry out work. Therefore yes it is ok, though most contractors will want to appoint a specialist designer depending on the size and complexity of the work. The key consequence to ensure is that the design obligation is based on skill and care (which is insurable) not fitness for purpose whi8ch is the general standard for the construction activities (and is not readily insurable).
answered Dec 1, 2017 by Rob Horne (18,680 points)