Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,545 questions

4,798 answers

791 comments

Register its Free

Download here

NEC ECC - How a Contractor gain profit under option A

0 votes
114 views
I have worked in different options in NEC but just had a question that how the contractor will get a profit if they have chosen Option A.  
From my understanding and the terminology of the contract is 'Option A is a priced contract with an activity schedule where the risk of carrying out the work at the agreed prices is largely borne by the contractor.

So the contractor is well aware that he is taking a risk while choosing the contract but wondering how the contractor will make money in this type of contract. Please can you explain. Many thanks. Kishore
asked Oct 19, 2017 in NEC3 General by Kishore  

1 Answer

+1 vote
 
Best answer
Firstly they will include risk and profit within their tendered lump sum fixed price, and if they manage the works well they will make money.

In terms of compensation events the Contractor will apply their fixed fee tendered in contract data part 2 to any elements of Defined Cost in building up their quotation.
answered Oct 19, 2017 by Glenn Hide (60,030 points)