Can an assessment of a compensation event be revised if a forecast upon which the assessment is based is later shown to have been wrong?

+1 vote
364 views
Can an assessment of a compensation event be revised if a forecast upon which the assessment is based is later shown to have been wrong?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The assessment of the compensation event is not revised.  The only circumstances in which a review is possible are those stated in Clause 61.6 (see Clause 65.2).