NEC ECC: Option A clause 11.2(27) what does it mean when you add the words "or partially completed" after the word "completed" (x3) in this clause?

+1 vote
55 views
How is PWDD calculated when it is not just completed activities but also partially completed activities as the sum for the total of the Prices each month?
asked Oct 7 in NEC3 Z clauses by anonymous   1 4
   

1 Answer

+2 votes
Don't know why an Employer would add in the words "partially" in that clause as a Z clause. The whole idea is it is a clear measure - only completed items are paid for, which is why the Contractor should break down their activity schedule to a reasonable level of detail.

You ask what it means when you add those words - the answer is subjectivity, so the advise is don't!
answered Oct 7 by Glenn Hide (33,000 points)