Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,868 questions

6,316 answers

1,502 comments

Register its Free

Download here

NEC ECC: Option A - Activity schedule changes to prices for the Price of work done to date

+1 vote
294 views
Assessing the amount due at the assessment date

A Contractor has asked for an extension of time to prepare a quotation for a compensation event which has occurred, however, when their application for payment is submitted they have included a "price"  against the event, even though no quotation has been submitted

Am I correct in when assessing the amount due at the assessment date only  quotations that have been submitted are able to be included on the Activity Schedule, as the Prices on the Activity Schedule cannot be changed unless a quotation has been submitted.

So, changes to Prices for Quotations that have not been submitted cannot be included as a completed activity on the Activity Schedule, even if the activity is completed?
asked Oct 3, 2017 in Payment by anonymous  

1 Answer

+1 vote
 
Best answer
You are correct - a Contractor is paid for completed items on the activity schedule, and a compensation event does not make the activity schedule until it is implemented.
answered Oct 3, 2017 by Glenn Hide Panel Member (87,180 points)