Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,547 questions

4,800 answers

791 comments

Register its Free

Download here

NEC Supply Contract: Who is a Subcontractor?

0 votes
92 views
Under the Supply Contract the definition of a Subcontractor is “organisation who has a contract with the Supplier to 1) supply part of the goods and services or 2) provide plant and materials which the person or organisation has wholly or partly designed specifically for the goods.

If I am making precast concrete units and have a concrete supplier and someone providing steel  reinforcement, do either fit the definition of a Subcontractor and hence need accepting?

Judging by the wording of 2) it sounds like off the shelf materials not designed specifically for the works should not need acceptance, but could they not be argued that they are supplying part of the goods and therefore fall under 1) although I assume not? And if not, what is 1) specifically to pick up?
asked Sep 13, 2017 in NEC3 General by anonymous   1 18 32

1 Answer

0 votes
 
Best answer
I agree with you on point 2.

On point 1, 'goods' is in italics, so is written Contract Data part 1 by the Purchaser. So if you subcontract says that the Supplier is to provide say "concrete for >insert main contract 'goods' wording" or something similar, then I think they probably would count as a Subcontractor and hence need accepting.

At the other extreme, if it was a standard contract to supply concrete which could be used on any precast units, then probably not.
answered Sep 13, 2017 by Jon Broome (46,270 points)