Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,331 questions

4,533 answers

597 comments

34,879 users

Register its Free

Download here

Claiming for losses when scope of work is reduced

+1 vote
106 views
The Client issued drawings late and procurement of reinforcement steel was based on BOQ. however as the project progresses the concrete quantity in the BOQ at tender is half the total concrete on completion and 50% of the steel will not be used. Is there a way of claiming compensation under NEC 3. Which clauses cover such a risk.
asked Aug 17, 2017 in NEC3 and NEC4 Contracts by brianmukoyi (130 points)  
   

1 Answer

+1 vote
Yes.

For a start, I assume that the date for issue of the drawings was either in the Works Information &/or the Accepted Programme. That would be a compensation event under clause 60.1 (5).

You could also argue that the PM is changing the Works Information. That would be c compensation event under 60.1 (1).

Finally look at option B clause 60.4, for a reduction in quantities. While its application would mean that you receive less overall, it may well entitle you to a re-rat to recover the overheads included in your original rate.
answered Aug 18, 2017 by Jon Broome (25,720 points)