Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,761 questions

6,181 answers

1,431 comments

Register its Free

Download here

What happens when a Contractor’s quotation is treated as having been accepted by the Project Manager (i.e. when the Project Manager has not replied to the Contractor’s quotation)?

+1 vote
366 views

What happens when a Contractor’s quotation is treated as having been accepted by the Project Manager (i.e. when the Project Manager has not replied to the Contractor’s quotation)?

asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

A compensation event is implemented when a Contractor’s quotation is treated as having been accepted by the Project Manager (see Clause 65.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)