Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,403 questions

4,622 answers


Register its Free

Download here

NEC ECS: Providing grounds for rejecting a nominated Subcontractor

+1 vote
We have been instructed to go under contract  with a Subcontractor for scope which falls outside of our current Works Information, the reason being to provide a payment vehicle for the PM who tendered the works but are unable to put on their internal procurement system,  due to the ambiguity surrounding liability we do not wish to place a contract with this Subcontractor, especially if they do not perform, can we reject providing grounds for rejection or do we simply have to accept under 14.3
asked Aug 4, 2017 in NEC3 General by David Roche (740 points)  

1 Answer

+1 vote
Best answer
You can reject for any reason - but if that is not a valid reason under the contract then this will be a compensation event. Any increase cost the subcontractor will incur for going elsewhere they can recover under that compensation event but you at least get what you want/need as well (all be it you may have to pay for it) .
answered Aug 4, 2017 by Glenn Hide (56,340 points)