Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,765 users

Register its Free

Download here

NEC ECSC: Can a Compensation Event occur after defects date

0 votes
96 views
We have completed a project under ECSC contract and the defects date has now passed but an event has occurred which would ordinarily be a CE under clause 60.1(14).

I appreciate that clause 61.5 states that "A compensation event is not notified after the defects date", however is there any mechanism which would allow this event to be considered or notified as a CE after the defects date.
asked Aug 4 in NEC3 Compensation Events by Sean (170 points)  
   

1 Answer

0 votes
As you state clause 61.5 sets out that a CE is not notified after the defects date however if both parties are in agreement to have the work carried out then clause 12.3 can be used to record the agreement.
answered Aug 4 by dave bates (5,350 points)