NEC3: TSC - Add new item not in Price List is compensation event?

0 votes
75 views
NEC3 Term Service Contract - The service manager would like to use a new method of cleansing which is not included in the service information or Price List . Is the introduction of a new item using the new method a compensation event?
asked Jul 31 in NEC3 Compensation Events by Dadpong (190 points)  
   

1 Answer

0 votes
Yes. As the Service Manager is asking you to do something which is not in the Service Information, they are effectively asking you for a quotation for a proposed instruction (under clause 61.2) which would change the Service Information.

As there is no rate for this, it cannot be assessed under clause 63.1 of the TSC, so would revert to clause 63.2.
answered Jul 31 by Jon Broome (25,100 points)