Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,767 users

Register its Free

Download here

NEC TSC: Service Manager - Delegated powers

+1 vote
45 views
Is their any hierarchy in decisions made by the Service Manager and those with delegated powers? For example can a client representative with delegated powers reverse a decision made by the Service Manager?
asked Jul 25 in NEC3 General by Mark   1
   

1 Answer

+1 vote
No there is no hierarchy between original named person and that of a delegate. They carry equal weight. Any instruction by one or other would supersede the previous and in itself would be a compensation event if is an instruction changing the Service information (or Scope under NEC4)
answered Jul 25 by Glenn Hide (33,040 points)