Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,767 users

Register its Free

Download here

NEC ECC: A small area of new pavement construction has settled and is beginning to crack

+1 vote
122 views
A small area of new pavement construction has settled and is beginning to crack. This occurs before Completion of the works in an ECC Option A Employer-designed contract.
a. What do the Supervisor and Contractor do next and what measures would follow to correct the Defect?
b. Would your answer be any different if this was Contractor-designed works?
The Contractor wishes to appoint XYZ Ltd as a Subcontractor. The Project Manager writes to the Contractor stating that he believes this would be an unwise choice as XYZ Ltd have performed badly on previous contracts with other Contractors.
c. What could the Project Manager do regarding XYZ Ltd?
d. The Contractor says that if the Project Manager objects to XYZ Ltd he would incur additional cost which he would seek to recover as a compensation event. How should the Project Manager respond?
asked Jul 18 in NEC3 General by anonymous   1 4
   

1 Answer

+1 vote
a. The Supervisor, PM and Contractor should discuss the situation to see if they can agreed what the cause of the issue is. If it is unclear the Supervisor should instruct the Contractor to search for the Defect ie trial holes to ascertain what has caused the settlement. If it was a design related issue then it would not be a Defect.
b. Yes, if it was Contractor design then it would be a Defect.
c. Unless the PM can justify that the subcontractor would not let the Contractor Provide the Works (clause 26.2) then the PM should just record his concerns.
d. as c
answered Jul 18 by dave bates (5,350 points)  
Just a point to add to Dave's response.  The PM's acceptance of a Subcontractor does not shift responsibility for the related management and performance onto the PM, as the Contractor remains responsible for Providing the Works.  Clause 26.1 further reinforces this point to state that the contract applies as if a Subcontractor's employees and equipment were the Contractor's.