Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,767 users

Register its Free

Download here

NEC ECC: Contractor Revision of PM Asssessed CE

+1 vote
84 views
I have a scenario on a project carried out under NEC3 ECC Option B. See below:

1- Contractor carries out additional work instructed under PMI and did not issue a CE until the work was completed, due to programme pressures.
2 - PM does not accept Contractor CE and opts to carry out his own assessment
3 - Value of CE is reduced through PMA due to unsubstantiated costs presented.
4 - Contractor does not notify the PM of there position on PMA CE value (i.e. intention to move to adjudication). In addition, the Contractor does not attempt to provide any further substantiation of costs presented within CE, i.e. sub-contractor invoice costs.
5 - The Contractor has now chose to re-submit the CE (2 Months after PMA) with both  additional costs not initially included and sub-contractor invoices which relate to PMA.

I appreciate this scenario demonstrates poor administration of the NEC Contract, due to works being implemented without acceptance of quotation, however I would like to gain some opinion on the applicableness of Cl 65. The term "Forecast" appears to be causing some discussion within this scenario, as the works have already being completed.

Has anyone ever had any experience of this before?
asked Jul 16 in NEC3 and NEC4 Contracts by NECUSER1988 (130 points)  
   

1 Answer

0 votes
Unfortunately this is quite a common situation in practice, which highlights the need to follow the procedures in the contract to avoid such 'problems' from arising.

From what you have said, if the PM's assessment has been notified to the Contractor, including providing details of the assessment, then the compensation event has already been implemented.

The Contractor's re-submitted quotation (referred to as CE in point 5) doesn't relate to anything because there is no 'open requirement' on which to link the quotation to, so the PM is under no obligation to do anything with it.

If the Contractor was 'too busy' at the time to submit a quotation, then there was an opportunity to extend the 'action time' by agreement.

The next step should be adjudication.

With reference to 'forecast', this should not be a difficult issue, especially if there are details provided with the assessment, including details of how the forecast was made.  Unfortunately most of the time a forecast is based upon a vague, subjective opinion, which naturally leads to disagreement.  A forecast should (and can) be calculated in a logical and methodical manner, using relevant cost data and information and by sensibly projecting this forward to a defined point in time, taking account of any specific issues which may influence the outcome, ie: access restrictions, working hours, Contractor's weather risk, co-ordination with Others etc.  No amount of 'experience' or 'expertise' can produce an accurate forecast without sensibly considering this process.  The 'experience' part is essentially a sense check on the outcome, rather than just churning out numbers.

Take a weather forecast, for instance.  It is based on a simulation of current trends and projected forwards in time, taking account of any particular localised conditions.  It is not always correct but usually not that far out, unless it is projected a long way forward in time where small variables may cause a different outcome.

It doesn't matter if a forecast differs from actual, it usually will as it is subject to 'variables' and is not an exact process, although more important is that it has been assessed correctly and properly.
answered Jul 18 by Andrew WI (3,510 points)