Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,102 questions

5,447 answers

1,162 comments

Register its Free

Download here

What happens when the Project Manager has notified the Contractor of his own assessment of a compensation event?

+1 vote
370 views
What happens when the Project Manager has notified the Contractor of his own assessment of a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager implements the compensation event by notifying the Contractor of his own assessment (see Clause 65.1).

answered Oct 9, 2012 by BuiltIntelligence (840 points)