What happens when the Project Manager has notified the Contractor of his own assessment of a compensation event?

+1 vote
375 views
What happens when the Project Manager has notified the Contractor of his own assessment of a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager implements the compensation event by notifying the Contractor of his own assessment (see Clause 65.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)