NEC ECC: Is there provision is included in the NEC for nomination of subcontractors

+1 vote
670 views
asked Jun 21, 2017 in Title by mafika  

1 Answer

+1 vote
 
Best answer
No. Reason is that if the Employer really wants a particular specialist contractor, rather than create a shotgun marriage where contractually the Subcontractor is answerable to the main Contractor but commercially (sort of) to the Employer, the Employer should control the interface themselves.
answered Jun 21, 2017 by Jon Broome Panel Member (61,270 points)