Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,211 questions

5,571 answers

1,215 comments

Register its Free

Download here

NEC ECC: Is there provision is included in the NEC for nomination of subcontractors

+1 vote
531 views
asked Jun 21, 2017 in Title by mafika  

1 Answer

+1 vote
 
Best answer
No. Reason is that if the Employer really wants a particular specialist contractor, rather than create a shotgun marriage where contractually the Subcontractor is answerable to the main Contractor but commercially (sort of) to the Employer, the Employer should control the interface themselves.
answered Jun 21, 2017 by Jon Broome Panel Members (57,430 points)