Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,335 questions

4,537 answers

598 comments

34,898 users

Register its Free

Download here

NEC ECC: Option C - Quotation vs. Actual

0 votes
84 views
On an Option C Target Cost contract, if a Compensation Event arises and the Contractor issues a quotation which is accepted then the Target Price is increased by that amount. In carrying out the additional work is the Contractor paid the cost of the accepted estimate or the actual cost -  be that higher or lower than their estimate?
asked Jun 2, 2017 in NEC3 and NEC4 Contracts by PJ  
   

1 Answer

0 votes
Yes that is correct! Under option C the cost of under-spend/overspend is shared and that is the same for implemented compensation events.
answered Jun 2, 2017 by Glenn Hide (33,750 points)  
Response from question author:
So if the total of the prices is increased by the value of the accepted quotation for the CE, what is to stop the Contractor from quoting a very high CE. For example on an original  1m target cost contract, suppose a 20k quotation is accepted but the actual work only costs 10k. The target would move to 1.020 but the actual cost would be 1.010 - there is a 'saving' against the target of 10k and they would gain a share of this - say 5k on a 50/50. If the above is correct, is this a realistic strategy and how could it be controlled?
Nothing stops the Contractor from putting in a high quotation - but nothing then stops the Project Manager from making their own assessment to something more sensible/reasonable.
NEC ECC: Amount paid under option C CE's