Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,305 questions

4,506 answers

589 comments

34,752 users

Register its Free

Download here

NEC TSC - Calculation of Late Interest

+1 vote
97 views
In the contract data the rate for interest on late payment is stated to be 1% per annum over base lending rate for the BoE.
Clause 51.2 states that interest is calculated at the rate stated in the Contract Data...of the delayed amount per complete week of the delay.
How do the words per annum affect the calculation of the interest?
Had the Contract Data not had this insertion, the calculation on a £ 30,000 payment for 10 weeks would have been £ 30k x 0.5% = £ 150 x 10 weeks = £ 1,500.
Given the insertion of the 1 % per annum rate ( and assuming BoE lending at 0.5% ) is the correct calculation :
1. £ 30k x 1.5% x 10weeks = £ 4,500 or
2. £ 30 x 1.5% = £750 x 10/52 = £ 86.54
Quite a difference !
Do the words 'per complete week of delay' in clause 51.2 apply to the rate stated in the Contract Data even though the CD rate uses the words 'per annum'?
asked May 6 in NEC3 Payment by VXI5445 (130 points)  
   

1 Answer

0 votes
the calculation is method 2 however £30K x 1.5% is £450, the £86.54 is right.

complete week means that it needs to be a complete week eg 9.5 weeks would be 9 weeks
answered May 7 by dave bates (5,330 points)  
Apologies for the typo re £750 vs £450.
On reflection, given that the Contract Data doesn't make mention of the 'per complete week of delay' and simply states a per annum interest rate then the correct calculation would be on a daily basis.