Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,766 users

Register its Free

Download here

NEC ECC: Interest due to the Employer from overpayment to the Contractor

+1 vote
53 views
If the PM corrects an amount due in favor of the Employer, are they entitled to interest on the corrected amount (over-payment)?
asked May 2 in NEC3 Payment by anonymous   1 4
   

1 Answer

+1 vote
Clause 51.3 deals with interest on corrected amounts. The clause is silent on which party pays therefore can be either party. In the context of the second bullet point this makes sense as adjudication / tribunal decisions could go either way.

Note that the clause is very specific as to the things that will attract interest (mistake, compensation event, adjudication / tribunal decision) therefore not all corrections of an amount due will attract interest, you need to look at why the correction was needed to determine this.
answered May 2 by Neil Earnshaw (7,460 points)