Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,767 users

Register its Free

Download here

NEC ECC: If a reason for a CE is deleted can the Contractor claim for it elsewhere?

+2 votes
70 views
If 60.1(12) is deleted as a Z clause, what stops the Contractor claiming for the same event under 60.1(19)?
asked Apr 21 in NEC3 Time by anonymous   1 4
   

1 Answer

+2 votes
I doubt you'd have success with this approach.

By deleting the express provision of the contract that deals with physical conditions the intent of the Employer was clearly to transfer this risk to the Contractor rather than make it the subject matter of another compensation event by implication.

The Guidance Notes say clause 60.1(19) is a force majeure event which wouldn't ordinarily include physical conditions.

Also the test to apply is strict, there are five bullet points under clause 60.1(19) and you need to prove that four of them are true for you to have a compensation event. The third bullet point would be your most difficult to overcome, " which neither Party could prevent" - was their nothing either the Contractor or Employer could have done to prevent you from encountering the physical conditions you experienced? I suspect the answers will usually be yes, especially from the Employer.
answered Apr 21 by Neil Earnshaw (7,460 points)