Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,366 questions

5,756 answers

1,276 comments

Register its Free

Download here

NEC ECC: Risk allocation - how is it allocated or capped?

+1 vote
1,077 views
If the contractor has allocated say £10k for existing structures under the ECC and it actually comes out at £60k is the Contractor liable to pay this? Can a Contractor cap his risk pot/allocation for certain risks at a figure?
asked Apr 5, 2017 in Risk and Insurance by anonymous   10 59 88

2 Answers

+2 votes
 
Best answer
In very simple terms, there are two methods of allocating risk in the ECC :

1. by adding or deleting compensation events. These directly impact on what is included or excluded from the Prices. If no compensation events have occurred, then just because something costs a lot more, does not mean the Prices are adjusted.
 
2. by choice of payment option which affects how over or under runs of cost relative to the Prices are - or are not - shared. So, in your example, if it was an option A Priced Contract, all the pain would be on the Contractor; if it was an option C target contract, then the pain would be split by the sharing formula; if it was an option E cost reimbursable, it would be on the Employer.

So can the Contractor cap his liability ? Depends on the contract he signed up to.
answered Apr 6, 2017 by Jon Broome Panel Member (60,470 points)  
selected Mar 1, 2018 by Glenn Hide
0 votes
Part of the answer will depend upon the Option you are working under and what the specific risk is.

If the risk is the amount of repairs to the existing structure then then under Option A it is the Contractor's risk and yes he is liable to pay. If it is an Option B then you will need to review the bill of quantities for how the work is measured. If it is Option C then the risk is shared through the gainshare arrangements. If it is Option D then need to review the bill of quantities for how the work is measured.
answered Apr 6, 2017 by dave bates Panel Member (14,180 points)