Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

What happens if the Project Manager does not reply within two weeks of receiving the Contractor’s notification?

+1 vote
363 views
What happens if the Project Manager does not reply within two weeks of receiving the Contractor’s notification?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

+1 vote
 
Best answer

The notification is treated as acceptance by the Project Manager of the Contractor’s quotation (see Clause 64.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)