What happens if the Project Manager does not reply within two weeks of receiving the Contractor’s notification?

+1 vote
357 views
What happens if the Project Manager does not reply within two weeks of receiving the Contractor’s notification?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

+1 vote
 
Best answer

The notification is treated as acceptance by the Project Manager of the Contractor’s quotation (see Clause 64.4).