Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,305 questions

4,506 answers

589 comments

34,752 users

Register its Free

Download here

JCT: (Sub contractor) If the main contractor doesn't respond to a final account disputes letter, what is the next step to take?

0 votes
50 views
asked Mar 8 in JCT Contracts by anonymous   1 4
   

1 Answer

0 votes
I am assuming that the MC has issued the final account to the SC and the SC has said that it is wrong. The next formal/contractual step will be for the SC to formally challenge the final account valuation by adjudication or the dispute method set out in the contract.
answered Apr 5 by Rob Horne (9,530 points)