Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,327 questions

5,703 answers

1,262 comments

Register its Free

Download here

How long does the Project Manager have to assess the compensation event after receiving the Contractor’s notification?

+1 vote
341 views
How long does the Project Manager have to assess the compensation event after receiving the Contractor’s notification?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager has two weeks within which to reply to the Contractor’s notification (see Clause 64.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)