How long does the Project Manager have to assess the compensation event after receiving the Contractor’s notification?

+1 vote
354 views
How long does the Project Manager have to assess the compensation event after receiving the Contractor’s notification?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager has two weeks within which to reply to the Contractor’s notification (see Clause 64.4).

answered Oct 9, 2012 by BuiltIntelligence (870 points)