Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,331 questions

4,533 answers

597 comments

34,877 users

Register its Free

Download here

Creating Float on the Critical Path

0 votes
161 views
Our Client says that if we speed up on the critical path and pull the Planned Completion Date in by say 1-week then we should add this time as Terminal Float at the end of the programme.

I thought if this happened all we created was Total Float which could be used by both, whoever gets there first.

I know that if I had TRA on the critical path activity and did not use it I could add this as Terminal Float at the end, but not if I did not have any TRA on the activity.

I would like to increase my Terminal Float but don't think the contract allows this.  What is the right way to do this.
asked Dec 20, 2016 in NEC3 Time by Gordon Proudfoot (220 points)  
   

2 Answers

0 votes
Your client is correct.

The time between Planned Completion and the Completion Date is Terminal Float (though the NEC doesn't use the term Terminal Float and doesn't define Planned Completion) and this 'belongs' to the Contractor.

If you advance Planned Completion for any reason - whether that is not needing TRA, bringing in additional resource and completing work earlier, or re-scheduling and completing activities earlier - you increase Terminal Float.
answered Dec 21, 2016 by dave meller (940 points)  
0 votes
if your are able to advance planned Completion through better performance reprogramming etc then the gap produced between this earlier date and the Completion Date is "terminal float" and belongs to the Contractor (presuming that planned completion is earlier then the Completion Date).
answered Dec 21, 2016 by dave bates (5,450 points)