So, is this correct to say, in a nutshell, that;
- Unused TRA on activities on the critical path is to be transferred to terminal float.
- Unused TRA on activities not on the critical path is to be transferred to total float.
So, is this correct to say, in a nutshell, that;
Yes in a nutshell that is correct!