Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,327 questions

5,703 answers

1,262 comments

Register its Free

Download here

What happens if the Contractor does not notify the Project Manager that he has failed to assess a compensation event within the time allowed?

+1 vote
346 views
What happens if the Contractor does not notify the Project Manager that he has failed to assess a compensation event within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

+1 vote
 
Best answer

This is then a late reply compensation event as per Clause 60.1(6).

answered Oct 9, 2012 by BuiltIntelligence (870 points)