What happens if the Contractor does not notify the Project Manager that he has failed to assess a compensation event within the time allowed?

+1 vote
355 views
What happens if the Contractor does not notify the Project Manager that he has failed to assess a compensation event within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

+1 vote
 
Best answer

This is then a late reply compensation event as per Clause 60.1(6).

answered Oct 9, 2012 by BuiltIntelligence (870 points)