Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,201 questions

5,563 answers

1,215 comments

Register its Free

Download here

NEC3 ECC: Option A - amending an Activity Schedule

0 votes
328 views
If the Project Manager implements an negative CE for the omission of works am I correct in amending Activity Schedule to suit as these activities will no longer appear on the accepted programme therefore becoming an errant activity?
asked Oct 9, 2016 in Main options by EH   2

1 Answer

0 votes
 
Best answer
Yes you can submit a revised activity schedule to reflect the omission of works. Any such omission is assessed using Defined Cost, rather than the identified figure on the activity schedule (where one exists) UNLESS both Parties agree. The Contract is fairly quiet on how specifically this is done in actually physically changing the activity schedule but as long as it adds up to the correct number there is unlikely to be too much issue in accepting the revised one.
answered Oct 10, 2016 by Glenn Hide Panel Members (75,330 points)