Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,335 questions

4,537 answers

598 comments

34,898 users

Register its Free

Download here

NEC3 ECC: Rainfall - Weather CE

0 votes
143 views
In a the following scenario, can someone provide guidance if indeed the PM was to make an assessment. Contractor notifies a CE due to rainfall exceeding one in ten year data. The weather centre issues out that the average number of days rainfall at the place stated in the Contract Data > 5mm is 4 days; one in ten is 9 days (>5mm) and the weather data determines that ten days in that month, the rainfall exceeded 5mm. Is is the difference between the 10 days and the average or the 10 days and 9 days that trigger the one in ten?
asked Aug 30, 2016 in NEC3 Compensation Events by MCZ  
   

1 Answer

0 votes
It is the difference between the 1 in 10 value and the actual data. The compensation event should then assess the impact of this extra days rain as to what it had in terms of time and cost. In practice this is usually very difficult/subjective to definitively determine the specific impact of this one day - but that is what the Parties have to try to determine.
answered Aug 30, 2016 by Glenn Hide (33,750 points)