Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,618 questions

4,886 answers

829 comments

Register its Free

Download here

JCT Named Subcontractor

+1 vote
249 views
Under a live JCT ICD, if a client or architect obtains a subcontractor quote for a specialist package of work and the main contractor agrees to employ the specialist (eg for a glazing package); what responsibility if any does the client retain for the subcontractor? Or are they seen as a domestic subcontractor with the main contractor taking full responsibility? They were not formally Named under the contract.
asked Jul 15, 2016 in General by anonymous   2 24 38

1 Answer

+1 vote
 
Best answer
This seems like a situation more likely to be a domestic subcontractor. From what you say there is no requirement or imposition on the contractor to appoint this particular subcontractor.  If there was a compulsion to use the identified subcontractor then the Employer may retain some liability for quality and time/cost overruns but I would need more detail to give guidance on that.
answered Aug 25, 2016 by Rob Horne (18,590 points)