NEC3 ECC: Issuing Certificates

+1 vote
841 views
Clause 30 states that the Project Manager certifies completion.

Similarly, clause 43 states that the Supervisor issues the Defects certificate.

However, neither clause says who the certificate are issued to.  Are they issued to the Contractor and copied to the Employer or vice versa?
asked May 27, 2016 in NEC3 Time by Brian (510 points)  
   

2 Answers

+2 votes
I believe that the answer is in clause 13.6 which states

The Project Manager issues his certificates to the Employer and the Contractor. The Supervisor issues his certificates to the Project Manager and the Contractor.
answered May 30, 2016 by dave bates (5,450 points)  
+1 vote
I wrote this out - Clause 13.6 states "The Project Manager issues his certificates to the Employer and the Contractor. The Supervisor issues his certificates to the Project Manager and the Contractor." - then spotted Dave's answer waiting for approval below.
answered May 30, 2016 by Jon Broome (25,720 points)