When does the period that the Project Manager has to notify the Contractor of his assessment of an even begin?

0 votes
313 views
When does the period that the Project Manager has to notify the Contractor of his assessment of an even begin?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

This period starts when the need for the Project Manager’s assessment becomes apparent (see Clause 64.3).

answered Oct 9, 2012 by BuiltIntelligence (870 points)