NEC3 ECC: Is a programme accepted by default?

+1 vote
169 views
If the PM does not accept or reject a clause 32 programme in the allotted time, does this become the accepted programme by default?
asked Apr 22, 2016 in NEC3 Time by Paul Minton-Rowlands  
   

1 Answer

0 votes
This is a really easy one to answer! No, there is no mechanism for default or deemed acceptance of the programme it needs to be a positive acceptance.