Must all Compensation events be related to a particular item in Works Information? Or can it be time related only due to delay in information from the Employer? A substantial delay has been caused by delay in information in regards to structural steel design.
1 Like
Not all compensation events relate to the Works Information. Your example could fall under 60.1(5) if the need for the information was included on the Accepted Programme.