NEC3 ECC: Relationship between compensation events and Works Information

Must all Compensation events be related to a particular item in Works Information? Or can it be time related only due to delay in information from the Employer? A substantial delay has been caused by delay in information in regards to structural steel design.

1 Like

Not all compensation events relate to the Works Information. Your example could fall under 60.1(5) if the need for the information was included on the Accepted Programme.