NEC3 ECC: 12 Month Contract - Do you get paid 12 equal payments for P&G or prorata to value of work certified. Option B NEC3

+1 vote
200 views
asked Apr 9, 2016 in Payment by Kobie  

1 Answer

0 votes
 
Best answer
If prelim or management type activities are a separate item on an option B bill of quantities then you get paid as per the rules of option B i.e. the proportion of the work done at the rate stated. If it was listed as a lump sum item then the Contractor only gets paid when that item is complete (like an activity schedule item in option A).
answered Apr 9, 2016 by Glenn Hide Panel Member (78,720 points)