NEC3 ECC: Clause 62.6 late Project Manager response to compensation event quotation.

+1 vote
1,698 views
The Contractor has 'auto-implemented' their CEQ due to no response from the PM within the period for reply detailed in the contract.

The reason for the late response was due to ongoing discussions regarding the CEQ,
however no formal extension was requested.

Is there any recourse open to the PM to revist the CE quotation?
asked Mar 29, 2016 in Compensation Events by ih29339 (230 points)  

1 Answer

0 votes
 
Best answer
It is not clear if the Contractor has followed the "reminder" process within your example. According to clause 62.6 of the contract, if the Project Manager has not responded to the quotation within two weeks (unless amended) then the Contractor MAY notify the Project Manager to this effect. Failure to respond to the reminder for a further two weeks would then mean that the quotation is "treated as having been accepted" i.e. deemed accepted.

The word MAY emphasizes that the Contractor does not have to do this, but then that the deemed acceptance does not kick in until two weeks after the reminder (when ever that is issued after the lack of initial response).  

If this has been followed as described above then it is Implemented and it is full and final. The only remedy the Employer then has is adjudication, but that will only be for mathematical errors etc rather than subjective elements like what risk allowance should have been included or how many men should have been used.
answered Mar 29, 2016 by Glenn Hide Panel Member (78,720 points)