NEC3 ECC: Is the Contractor paid for UK Public Holidays?

+1 vote
229 views
Under the terms of ECC Option C, is the Contractor paid for UK Public Holidays if they are not UK Nationals?  The Contractor concerned is working in the UK under a VISA but are based in USA.
asked Mar 22, 2016 in NEC3 Payment by anonymous   3 8
   

1 Answer

0 votes
The contractor should be paid people costs when he incurs people costs. If that is over a holiday or weekend it doesn't matter. The only caveat to that would be if there were an express term in the contract limiting site times.
answered May 16, 2016 by Rob Horne (9,570 points)