How long does the Project Manager have to notify the Contractor of his assessment of a compensation event?

0 votes
358 views
How long does the Project Manager have to notify the Contractor of his assessment of a compensation event?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager notifies the Contractor of his assessment of an event within the same period allowed for the Contractor’s submission of his quotation for the same event (see Clause 64.3).

answered Oct 9, 2012 by BuiltIntelligence (870 points)