Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,310 questions

4,511 answers

592 comments

34,767 users

Register its Free

Download here

NEC3 PM DISAGREES WITH CE EVALUATION/QUOTATION

+1 vote
281 views
Assuming the correct process has been followed by the PM requesting a quotation and a revised quotation; and the contractor has responded accordingly, what redress has the PM got should he/she disagree with the contractors assessment. Bearing in mind the practicalities of keeping the job moving along
asked Jan 22, 2016 in NEC3 Compensation Events by BryanL (140 points)  
   

1 Answer

+2 votes
Project Manager should make their own assessment if they do not believe the quotation to be correct. Assuming these works have already been instructed under 61.1, the works should be proceeding anyway. The process you describe here is a parallel process to see how much the Contractor should be paid, and what effect (if any) there should be on Completion Date.

If the Contractor does not agree with the assessment/implementation by the PM then their recourse is only through adjudication.
answered Jan 22, 2016 by Glenn Hide (33,040 points)