NEC3 ECC: What opportunity is there (if any) within the contract to "contra charge"

If Contractor does something that causes a problem, that then costs the Employer money/resource to sort out, is there a way of charging the Contractor for this additional cost that the Employer has had to incur? The issue that was caused was not a defect, and was not a compensation event. I am struggling to see where we can seek this recovery if there are no Z clauses to pick up on the issue?

1 Like

You are not specific as to what these additional costs are. However in the NEC any contra charge would be subject to the Notice of Intention to Pay Less (Y2.3) HGCR Act 96. You have to have a basis under the contract to payless stating the reasons e.g. a breach of contract which has caused the E to incur additional costs. You must also give the required notices as required.

Generally the recovery of losses to the Employer form the Contractors non performance will come from delay damages X7, assessment of the cost incurred b y the E for the C not providing things he is to provide in the WI (25.2), assessment of Eā€™s additional costs of the Contractor, missing a Key Date (25.3), repeating tests and inspections (40.6), uncorrected Defects (45.1).