Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,493 questions

5,897 answers

1,319 comments

Register its Free

Download here

NEC3 ECC: Who owns the float prior to a Key Date?

0 votes
551 views
From Clause 63.3 my interpretation of the float prior to a KD is that it is not as per the terminal float associated with Completion, therefore free float obviously the Contractor still owns his Time Risk Allowance.

This relates from the PM instructing change that affects a KD.
asked Nov 2, 2015 in Compensation Events by rgowen (220 points)  

1 Answer

+2 votes
 
Best answer
I will answer your question and also point out that you may have slightly confused other float terms within the same question.

Firstly, float prior to a Key Date IS as per the terminal float associated with Completion Date which is clarified in the second sentence of clause 63.3. The second sentence repeats the first sentence but replaces the words "Completion Date" with "Key Date" emphasising that it is the same rule, i.e. Contractor owns terminal float associated with Key Dates as well. Any such terminal float is owned by the Contractor and retained in the assessment of any compensation events.

Secondly it is better to use the term "total float" rather than "free float", free float being part of total float and either Party can use total float when assessing change/compensation events. Time risk allowances are risk the Contractor has allowed against their own activities for risk which are theirs ad their for owned by the Contractor.
answered Nov 2, 2015 by Glenn Hide Panel Member (80,660 points)