Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,761 questions

6,181 answers

1,431 comments

Register its Free

Download here

How is a compensation event handled if, when the Contractor submits quotations for a compensation event, the Project Manager has not accepted the Contractor’s latest programme?

0 votes
350 views
How is a compensation event handled if, when the Contractor submits quotations for a compensation event, the Project Manager has not accepted the Contractor’s latest programme?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager will assess the compensation event (see Clause 64.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)