How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?

0 votes
324 views
How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager will assess the compensation event (see Clause 64.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)